New College, Pontefract


Project Status:

Complete

Project Outline:
Extension to Science Block and replacement of central plant.

Description:
New Science block and refurbishment of existing laboratories, Boiler Plant and Catering Facilities.

Contract Duration:
45 Weeks

Contract Value:
Circa £850k

Services Provided:
The Mechanical (plumbing), Air-conditioning and Electrical fit out of the new Science Block Extension, Refurbishment of the existing catering facilities and associated Refectory including washrooms. Refurbishment of existing science laboratories over three floors. Replacement of old coal burning heating plant with Automated Silo Coal fired plant including complete new plant building and all associated diversionary works.

Main Contractors:
New College

End User:
New College Pontefract

Consultants:
2 Can

Completion Date:
April 2008

Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player